The City of Launceston will be undertaking spray sealing works at the following locations:
Line Removal: 11/03/2025 to 12/03/2025
Sealing: 17/03/2025 to 22/03/2025
Linemarking will occur between 25/03/2025 and 28/03/2025.
Line Removal: 13/03/2025 to 14/03/2025
Sealing: 25/03/2025
The works are planned to occur from 11 March 2025 to 22 March 2025, between 7:00 am and 5:00 pm, followed by linemarking. A reduced speed limit and occasional lane closures will be in place during working hours.
Please note that scheduling may change due to unforeseen circumstances or weather conditions. If conditions are unsuitable, the project will be rescheduled for the next suitable day.